Safety production is always on the road - Snow wave Environmental Engineering company firmly grasp the safety line

Release time:2021-09-17 Reading quantity:2267 Return list

Recently, Wuxi Snow waves Environmental Engineering Technology Co., LTD. (hereinafter referred to as the engineering company) held a special meeting on project safety, and the meeting proposed to be problem-oriented, focus on the key points, make up for weaknesses, strong and weak items, and promote the development of safety production work to the depth. Song Xin, vice president of Snow Wave Environment, general manager of engineering company, Tan Zhaoxia, deputy general manager of engineering company and project leaders attended the meeting.


The meeting briefed and commented on the recent project site safety production inspection and the implementation of safety production work, analyzed and judged the current construction site safety production situation, and put forward relevant guidance.


Song Xin, general manager of the engineering company, made a summary speech, he stressed that safety work is the premise of all work, we must focus on the implementation of weekly safety hazards investigation and rectification of the problem closed loop, safety production inspection normalization, effectively do all kinds of risk prevention and control, and resolutely curb the occurrence of safety accidents.




Half a month since the meeting


The project managers on site strictly implement the meeting requirements


Safety hazards were investigated in 53 projects under construction


Check and fill gaps in time


Close the hidden danger rectification loop


image

Before rectification: the ladder guardrail of the dust collector was not installed in time.


After rectification: Install ladder guardrail to implement safety protection.


image

Before rectification: Acetylene bottle without shading measures.


After rectification: Cover the sun visor.

 


image

Before rectification: dust collector scaffold is not standard, no acceptance certificate.


After rectification: set the end protection according to the requirements of the code, set the waist bar, after acceptance, the suspension scaffold acceptance certificate.


image

Before rectification: Small objects at the top of the wet tower are discarded at will, and there is a serious object strike security risk.


After rectification: Clean up the small debris on the platform of each layer, set up a small bucket for special placement, and do not throw it randomly.




According to the spirit of the meeting, the engineering company will further sort out the working mechanism and process, implement the main responsibility of safety production, consolidate the foundation of safety management, implement the responsibility of safety production, promote the participation of all employees in safety management, and form a good atmosphere for everyone to understand safety and prevent hidden dangers everywhere.


By Ni Chenxi, Xuelang Environmental Engineering Company